Notice to Contractors
X-26 SEWER & WATERMAIN RECONSTRUCTION NO.1 CITY OF APPLETON
THE CITY OF APPLETON HAS IMPLEMENTED ONLINE BIDDING USING THE QUEST CONSTRUCTION DATA NETWORK. ONLY ELECTRONIC BIDS WILL BE ACCEPTED THROUGH WWW.QUESTCDN.COM
The contract documents may be viewed and downloaded by registering with QuestCDN online (www.questcdn.com). Call (952) 233-1632 or email info@questcdn.com for assistance. This contract is Quest eBidDoc #9995566. Interested parties may view the contract documents at no cost on the QuestCDN website prior to becoming a plan holder. To be considered a plan holder for bids, a contractor must register on QuestCDN.com and purchase the digital contract documents. Registering as a plan holder is recommended for all prime contractors and subcontractors as plan holders will receive addenda and other contract document updates via QuestCDN.
For this solicitation, bids will ONLY be received and accepted via the online electronic bid service through QuestCDN.com. Download the bid documents and click the online bidding button at the top of the advertisement to access the electronic bid qualifications and bid worksheet. Bids must be entered and submitted by 1:45 p.m. (C.S.T) January 19, 2026. Bids will be read at 2:00 p.m. at City Center Building, Sixth Floor, 100 N Appleton Street, Appleton, WI 54911.
No bid will be opened unless the "Bidders Proof of Responsibility" for 2026 is filed in the office of the City Clerk not later than January 14, 2026. Forms are included in specifications and are also available at the office of the City Clerk. Reference is made to Section 66.0901 Wisconsin Statutes.
No bid shall be received unless accompanied by a certified check or a bid bond equal to five percent of the bid, payable to the City as a guarantee that if the bid is accepted, the bidder will execute and file the proper contract and bond within 10 days from the date the lowest responsible bidder's bid is accepted. If the bidder fails to file such contract and bond within the time set by the City, the check or bid bond shall be forfeited to the City as liquidated damages.
PROJECT
UNIT X-26
SEWER & WATERMAIN RECONSTRUCITON NO.1
134 Lin. Ft. F&I - 66" Steel Casing (Jack & Bore)
80 Lin. Ft. F&I - 24" Steel Casing (Jack & Bore)
92 Lin. Ft. F&I - 20" Steel Casing (Jack & Bore)
1200 Lin. Ft. F&I - 12" Watermain
1650 Lin. Ft. F&I - 8" Watermain
750 Lin. Ft. F&I - 1" Service
117 Lin. Ft. F&I - 24" CIPP Sanitary Sewer Liner
1400 Lin. Ft. F&I - 12" Sanitary Sewer
525 Lin. Ft. F&I - 8" Sanitary Sewer
400 Lin. Ft. F&I - 4"/6" Sanitary Lateral
1100 Lin Ft. F&I - 4" Trenchless Sanitary Lateral
75 Vert. Ft. F&I - 4' Dia. Sanitary MH
700 Lin. Ft. F&I - 48" Triple Wall HDPE Storm Sewer
375 Lin. Ft. F&I - 12" Storm Sewer
16.5 Vert. Ft. F&I - 8' Dia. Storm MH
38 Vert. Ft. F&I - 6' Dia. Storm MH
20 Vert. Ft. F&I - 4' Dia. Storm MH
350 Sq. Yd. R&R - 7" Concrete Pavement
100 Sq. Yd. R&R - 4" Concrete Sidewalk
400 Lin. Ft. R&R - Concrete Curb & Gutter
The City reserves the right to reject any and all bids or to accept any bid deemed for the best interests of the City and to waive any informalities in the bidding.
DATE: December 22, 2025
Amy Molitor, City Clerk
WNAXLP
January 2, 9 2026
LWIX0430149